Treatment plant nearing completion

August 17, 2011

Photo by Gian DeLoia – The Johnsonburg Municipal Authority discusses the progress of the waste water treatment plant.

JOHNSONBURG – The Johnsonburg Municipal Authority held their regular meeting Tuesday night to discuss the progress of the waste water treatment plant.
"The total project costs will stay within budget provided costs for extra engineering due to the most recent six months of delay are deducted from the general contractor's retainage," said engineer Dan Guss.
The incurred costs for the project as of July 1 are $14,199,677.33 out of a projected budget of $14,319,088.
According to Guss, the treatment plant has remained in full operation since May 31.
"Operating results have been very good and within DEP limits," Guss said.
Guss noted the "punch list" for McCrossin is down 100 items or less including all computer items.
The value of the punch list is less than $100,000, including $25,000 of spare parts to be supplied by the computer supplier.

Pick up a copy of the Wednesday, Aug. 17, 2011 edition of The Ridgway Record for more.

Next meeting
Johnsonburg Municipal Authority
Tuesday, Sept. 20
Municipal Office
6 p.m.

Ridgway boys golf won the team season opener 195-246 over Kane Tuesday afternoon on a hot afternoon...
Current Ridgway golfer Josh Roselli, representing Laurel Mill Golf Club, finished as the runner-up...
Current Ridgway golfer Josh Roselli, representing Laurel Mill Golf Club, finished as the runner-up...